Welcome to the New 6th form centre project Blog

"Welcome to the New 6th Form Centre progress Blog" The contents of the blog will be updated as it progresses through It's 20 week program.
" We are Just about Finished"

Friday, 15 February 2013

Latest pics

Entrance corridor
 
Mezzanine Ballustrade, awaiting etched glass

Thursday, 14 February 2013

Slight Delay

Due to the issues that were encountered with Asbestos and Unexpected steelwork propping A request has been made for a 2 week extension on the completion date. This was not unexpected and will not impact on the school plans to bring the block back into use. Other than this slight delay everything is progressing nicely I will update the site with some more pictures later today.

Tuesday, 12 February 2013

Still going strong

Work continues to press on, Plumbers electricians plasterers joiners all working together to move the project ever nearer to completion. The final pieces of stud work going up and internal woodwork will start to be fitted in the next week. I would expect heating to be completed by the middle of next week and the majority of the electrical work completed by then as well.

The new external entrance is out of the ground and should be complete by the end of the half term holiday. The next job will be the replacement of the large flat roof that covers the canteen area.
I will post a few pictures in the next day or so.

Wednesday, 6 February 2013

Cafe area Kitchen counter design

Below is an idea of how the counter area for the new canteen will look like, Final colours and exact detail still to be confirmed but along the lines of below.

"Going Up"

Stairs were delivered and erected on Monday, stud walls internally continuing to go up, Electrics, Security systems, Plumbing, all going in. The space is beginning to look more defined now.

Steel stairs concrete treads to go in.