Welcome to the New 6th form centre project Blog

"Welcome to the New 6th Form Centre progress Blog" The contents of the blog will be updated as it progresses through It's 20 week program.
" We are Just about Finished"

Monday, 18 March 2013

Paint

The upstairs of the renovation are in the final stages of completion, with the decorators just putting the finishing touches to the decor. we have gone for a bold heritage colour to feature walls and to highlight the ceiling beams. Once the carpets go down and the glass in th ballustrade is fitted it will be complete, ready for furniture.




Monday, 11 March 2013

General catch up

The painters are in, starting upstairs, there is quite a bit of work to be done so i imagine they will be here for the next 2-3 weeks. There is a small amount of plasterwork to be completed downstairs with the electrician on this last few bits. the new front doors have been ordered and I would expect to see them fitted sometime next week. All in all everything is progressing nicely.

Roof

Fitting the new roof over the canteen area and the new entrance start today, I bet they are pleased with the snow!  this will probably take all week to complete weather permitting.

Tuesday, 5 March 2013

Getting closer

The upstairs is just about ready for the painters to go in. Downstairs the new entrance is coming in the roof is just going on and the floor screed will be in shortly.

Below are the latest pictures

New Careers Library above old mac suite

 

Looking through top of the stairs to the new mezzanine
 
Looking at the new careers office from the mezzanine
 
From downstairs looking up the new staircase

 

Block work complete roof going on and floor screed going down soon.