Welcome to the New 6th form centre project Blog

"Welcome to the New 6th Form Centre progress Blog" The contents of the blog will be updated as it progresses through It's 20 week program.
" We are Just about Finished"

Wednesday, 30 January 2013

Progress


The floors upstairs are now just about complete, internal studwork will start soon and the staircase will follow over the next week or 2.





Doorways knocked through from mezannine.

- Posted using BlogPress from my iPhone

Thursday, 24 January 2013

Cafe Area

Below  gives you an idea of how the Cafe area will work within the cafeteria.





Supports removed

The expensive supports that held up the gable end while the new steelwork went in has now been removed.




Tuesday, 22 January 2013

Mezzanine


The mezzanine flooring is nearing completion, with the plasterers due to put in the new ceilings next week. the Electrician is in all this week doing the 1st fixing.

Awaiting plaster boarding



New floor down

Friday, 11 January 2013

Work continues

Work is well underway, the floor joists for the mezzanine floor are going in and should be complete early next week, the new block work wall is complete. Steelwork to support the main gable end wall was delivered this morning and will be going in next week. The new entrance to the canteen area has just been opened up and the footings for the new entrance are now in. Over the next week things will start to take shape.



Mezzanine floor joists going in


Block work wall complete


New massive steelwork


New canteen entrance being created