Below is an idea of how the counter area for the new canteen will look like, Final colours and exact detail still to be confirmed but along the lines of below.
Welcome to the New 6th form centre project Blog
"Welcome to the New 6th Form Centre progress Blog" The contents of the blog will be updated as it progresses through It's 20 week program.
" We are Just about Finished"
Wednesday, 6 February 2013
"Going Up"
Stairs were delivered and erected on Monday, stud walls internally continuing to go up, Electrics, Security systems, Plumbing, all going in. The space is beginning to look more defined now.
| Steel stairs concrete treads to go in. |
Wednesday, 30 January 2013
Progress
The floors upstairs are now just about complete, internal studwork will start soon and the staircase will follow over the next week or 2.
| Doorways knocked through from mezannine. |
- Posted using BlogPress from my iPhone
Thursday, 24 January 2013
Supports removed
The expensive supports that held up the gable end while the new steelwork went in has now been removed.
Tuesday, 22 January 2013
Mezzanine
The mezzanine flooring is nearing completion, with the plasterers due to put in the new ceilings next week. the Electrician is in all this week doing the 1st fixing.
| Awaiting plaster boarding |
| New floor down |
Friday, 11 January 2013
Work continues
Work is well underway, the floor joists for the mezzanine floor are going in and should be complete early next week, the new block work wall is complete. Steelwork to support the main gable end wall was delivered this morning and will be going in next week. The new entrance to the canteen area has just been opened up and the footings for the new entrance are now in. Over the next week things will start to take shape.
![]() |
| Mezzanine floor joists going in |
![]() |
| Block work wall complete |
![]() |
| New massive steelwork |
![]() |
| New canteen entrance being created |
Subscribe to: