Rilmac the Asbestos management company, arrived on site today to set up for the asbestos removal. It became apparent due the location of suspected asbestos and the confirmed asbestos removal, that no other works will be conducted until it has been removed. All site personnel have left the project until Monday morning, leaving Rilmac to get on with the asbestos removal. This involves erecting contamination chambers and is quite involved and highly regulated.
Other information:
Deadlines for ordering steelwork to support the wall that has been removed are extremely tight, If they can't be ordered next week there will be a knock on effect due to the christmas closedown period. It is imperative the structural engineer can amending his design to incorporate concrete in the floor as opposed to steel, this will enable orders to be placed and deadlines hit.