Welcome to the New 6th form centre project Blog

"Welcome to the New 6th Form Centre progress Blog" The contents of the blog will be updated as it progresses through It's 20 week program.
" We are Just about Finished"

Tuesday, 18 December 2012

Mezzanine

The main steelwork to support the mezzanine floor are now in place, flooring joists will be fitted into these shortly.
Two heavy duty RSJ beams


The stud wall at the end of C2 has been removed and will be replaced with a block work one



The concrete floor has been dug up ready for the steel and concrete to act as new foundation to support the steelwork for the large wall opening in the new canteen area as detailed in previous blog.